Implementation
The implementation followed the design very closely levelling the site, ground spikes,PVC piping, timber work, steel work taping,cover preparation and then instalment, pond, path then planting.
FOLLOW THE SIDE SHOW
FOLLOW THE SIDE SHOW
Time process PR4
This was 1 of the quickest projects to complete we had collected the materials be for we started and had arranged the extra people power we needed.
- Clearing the ground of vegetation and leveling the site 2 days. 2 people
- Steel tubing for ground spikes and bending cutting of the PVC piping and installing 1 day. 2 people
- Timber work , steel work 1 day 5 people
- PVC cover preparation and installation 1 day 9 people. (we had time for tea and cake)
- Path started 1 day (to be completed)
- Pond 2 hours 3 people
Tweak
There have been tweaks already with other ongoing the doors have been changed to mesh to help with ventilation and a path of bricks to help with heat storage in the winter and more timber battening for the end sections. I am sure many more will follow security issues have arisen due to vandalism.